An industrial area in Wattle Grove and City of Gosnells. 13% of MKSEA identified land is within City of Kalamunda’s boundaries. The MKSEA area in the City of Kalamunda is bounded by Welshpool Road East and City of Gosnells boundary.
In August 2014, the City of Gosnells (CoG) completed all necessary studies in support of the rezoning of the major portion of Maddington Kenwick Strategic Employment Area (MKSEA) within their boundaries, from ‘Rural’ to ‘Industrial’. 13% of MKSEA-identified land is within the City of Kalamunda’s boundaries. The MKSEA is bounded by Welshpool Road East and the CoG boundary.
May 2020Precinct 3C is a section of MKSEA zoned Industrial under the Metropolitan Region Scheme and under the Local Planning Scheme includes properties zoned Special Rural, Public Purposes and Private Clubs and Institutions respectively. Once an MRS Amendment is approved generally the Local Government is required to amend the Local Planning Scheme so the zoning is consistent. Given the Environmental Protection Authority (EPA) has directed the City of Gosnells to undertake an Environmental Review which may affect recommendations for Precinct 3C the City of Kalamunda has been granted a number of extensions by the WAPC pending outcomes of the review.
In the meantime the City of Kalamunda is progressing a number of technical studies, including a flora and fauna survey for Precinct 3C completed in Spring 2019. To view the full report see a copy below in Related Documents. ”
Figure 1: Precinct 3C flora and fauna survey boundary
June 2017In June 2017 Council resolved to adopt Scheme Amendment 89 that rezones the land from Special Rural to General Industry and Light Industry and to introduce a Special Control Area. View the June 2017 Council Report (item 32)The Special Control Area includes several conditions as detailed below:
The CoG requested the WA Planning Commission to initiate the Metropolitan Region Scheme Amendment to change the zoning from ‘Rural’ to ‘Industrial’. Following that, the City of Kalamunda requested the WA Planning Commission to include the remainder of the land identified under MKSEA within the City's boundaries in the Amendment. Our correspondence was sent to the WA Planning Commission in November 2014.
The key stages in the City of Kalamunda’s proposed planning for this area are anticipated to proceed as follows:
The draft Perth and Peel @ 3.5 million and associated draft North-East Sub-regional Planning Framework, the highest level strategic document for Perth and Peel, identified this area as a future Industrial Expansion area.Follow the links to the see the draft NE Subregional Framework document and plan
More information is available on the City of Gosnells website. For any queries regarding this project section, call the City’s Strategic Planning on 9257 9930.