The City of Kalamunda will be upgrading road surfaces on Hawtin Road, from Maida Vale Rd to Norwood Rd.
This is a two-part project which includes kerb replacement and road resurfacing.
Kerb replacement will commence first in late-February 2024 and is anticipated to take two weeks to complete. This is dependent on contractor availability and weather conditions.
The road resurfacing is scheduled for early-May 2024.
Properties located adjacent to the proposed works may experience some disruption in relation to exiting and entering the property during kerb replacements. If this situation should occur, then you are requested to contact the City’s kerb contractor1, in the first instance, who will then make the appropriate arrangements with you.
Please be assured that every effort will be made during these works to minimise impact on those who live nearby and also to the environment.
1 Contractor contact details were provided as part of the notification letters sent to the properties in the work-related area.
Stage 5: Temporary road closure on Hawtin Rd. Detours in place via Norwood Rd, Lilian Rd, Kalamunda Rd, Priory Rd, Maida Vale Rd, Myerson Cres, Brewer Rd, Kent Rd. Commencing 02 May until 04 May, from 8:00pm – 5:00am. With contingency dates for 09/05, 16/05, 23/05 and 30/05.
Stage 6: Temporary road closure on Hawtin Rd. Detours in place via Lilian Rd, Norwood Rd, Holmes Rd, Maud Rd, Kent Rd, Brewer Rd, Lychee Rd, Jecks Rd, Pimelea Rd. Commencing 02 May until 04 May, from 8:00pm – 5:00am. With contingency dates for 09/05, 16/05, 23/05 and 30/05.